Power Consulting Associates | Vicksburg 115kV Improvement Project

Power Consulting Associates provided civil engineering design services for Entergy’s Vicksburg 115kV Improvement Project crossing Warren and Hinds Counties, Mississippi. The project was approximately a 29 mile transmission line design build completed in four phases. This line design had significant challenges in each phase: crossing of a 500kV transmission line, crossing the Natchez Trace Parkway and Big Black River, and its proximity to John Bell Williams Airport. The final phase of the project included connecting the new Beech Grove Substation, including lattice tower replacement, tie-in work, and two new line sections built to reroute existing transmission line.